Construction Update for Mackworth, Ocean, Walton and Sawyer Streets

Construction Update: 04/28/2022

Gorham Sand & Gravel has returned to this project site to complete work over the next few months.  They will be working on curbing, ADA ramps, and raising manhole structures on Walton Street first then move to Sawyer Street. Later in May, once overnight temperatures are above 50, they will place loam and seed.  Other remaining work includes installing new trees on the affected streets.  Near the end of June and into July the contractor will start to prep Ocean Ave, Walton Street and Sawyer Street for surface paving and lane stripping.  The majority of the work will be completed by the end of July.  

Full Project Schedule, Updates and Graphics