The project is under construction by Gorham Sand and Gravel from Buxton ME. Construction will continue throughout 2021.
Construction Schedule (Updated 4/7/21)
TRAFFIC ADVISORY UPDATE 4/9/2021
Ocean Avenue: from Read Street to Forest Avenue will be One–Way Traffic Only & Walton Street: from Ocean Avenue School Entrance to Ocean Avenue will be One-Way Traffic Only
Beginning April 16, 2021
Construction update for the week ending April 7, 2021
Gorham Sand & Gravel continues to install temporary PWD water mains in preparation for upcoming water main work. Once the temporary main is active, work will start for Water, Sewer, and Storm Drain in Ocean Avenue.
Gorham Sand & Gravel has been installing PWD water valves in preparation for upcoming water main work. Starting next week they will begin to lay temporary water main. Once the temporary main is active, work will start up again for Water, Sewer, and Storm Drain in Ocean Avenue.
Gorham Sand & Gravel continues to install 30" RCP reinforced concrete storm drain as well as 12" PVC plastic sewer pipe in Ocean Ave. They are heading towards Walton Street.
Also this week, GS&G finished installing the new 8" PVC plastic sewer pipe in Sawyer St to replace the existing 8" Vitrified Clay Pipe which is full of roots.
Totals for the week: 71 feet of storm drain installed and 175 feet of sewer.
Gorham Sand & Gravel continues to install 30" RCP reinforced concrete storm drain as well as 12" PVC plastic sewer pipe in Ocean Ave. They are heading towards Walton Street.
Also this week, GS&G started to install the new 8" PVC plastic sewer pipe in Sawyer St to replace the existing 8" Vitrified Clay Pipe which is full of roots.
Totals for the week: 24 feet of storm drain installed and 130 feet of sewer.
Installing new sewer
Hammering ledge next to gas main
WHAT’S HAPPENING
New 10” – 48” storm drain and 8” – 12” sewer main will be installed within the following streets
Mackworth Street
Ocean Avenue (Walton Street to Forest Avenuet
Walton Street (Ocean Avenue to Canco Road)
Mayland Street
Irving Street
Sawyer Street
Forest Avenue at Baxter Woods
Hersey Street
Clifton Street (Hersey Street to Vannah Street)
Vannah Street
In total the project will construct 15,000 linear ft of new storm drain and new sewer main
New green infrastructure tree filters will be installed on Mackworth St and Walton St.
Streets within work area will be reconstructed, new pavement installed
New 1,590’ of 12” D.I. pipe, and approximately 3,690’ of 8” D.I. pipe water main on the project streets
Update: Curbing on Mackworth has been eliminated due to budget cuts.
Update: Sidewalk on Mackworth has been eliminated due to budget cuts.
WHAT TO EXPECT DURING THE PROJECT
Noise
Large equipment and machines moving through the area creating vibrations